Hi folks,
Just to let you know where we're at. Last Sat. the carpenter's union installed ceiling sheetrock; students from Cornell and Ithaca college worked on insulation in the walls and crawl space. The Wed. crew finished the fiberglass insulation in the walls - everyone did an excellent job on this; it looks like we should get a top rating on our energy star insulation evaluation.
This Sat. (9/19), the carpenters will be installing the sheetrock on the walls. We do have some other work that can be done at the same time - installing rigid foam in the crawlspace, and finishing exterior siding and trim work.
Next Sat. (9/26) we will not be working at the house. We plan on starting interior finish work in Oct.
Regards,Bruce