Update 9-4-09

Hi folks,

Thanks for the excellent work you've been doing. We're making very good progress so far.

Just wanted to update everyone on what's coming up.

Sat., 9/12 - carpenter's union is coming to put up ceiling sheetrock; Ithaca students will work on crawl space insulation in the afternoon.

week of 9/14 - wall insulation needs to be completed; air barrier sealing of ceiling sheetrock

Sat., 9/19 - carpenter's union will put up sheetrock on the walls

9/21-10/1 - sheetrock taping (we're still checking on someone to do this professionally, or at least the finish coat); attic insulation (blown cellulose)

10/2, 10/3, 10/7, 10/9, 10/10, 10/14, 10/16 - small groups (5-10) people will be coming from Corning, Inc. (MTE group) to work - potential tasks are (depending on progress): painting, installing laminate flooring, installing interior doors and bifold doors, installing window, door, and base trim, painting trim, installing closet shelving

With this in mind, I'd like to suggest we go back to working Wednesday, Friday and Saturday again beginning, Wed., 9/16.

Regards,
Bruce