Hi folks,
Many thanks to everyone who helped on this house at 89 Ontario St. We
could not have done it without all of you helping.
There will NOT be a regular work day this Sat. (11/21) - We will be
doing the final energy star testing & clean-up.
Don't forget the dedication and open house on Sun., (11/22) at 2 pm.
I'll keep you posted as we prepare for beginning the next house in
spring, 2010.
Regards,
Bruce
Friday, November 20, 2009
Thursday, November 12, 2009
11-12 UPDATE!
Hi folks,
We're hoping to get the major items finished up this weekend - including:
trim work, kitchen/laundry area (flooring, doors, trim) and
since the weather forecast looks good, lawn & site work outside
Regards,
Bruce
PS - Don't forget the house dedication on Sunday, Nov. 22, 2 pm
We're hoping to get the major items finished up this weekend - including:
trim work, kitchen/laundry area (flooring, doors, trim) and
since the weather forecast looks good, lawn & site work outside
Regards,
Bruce
PS - Don't forget the house dedication on Sunday, Nov. 22, 2 pm
Thursday, November 5, 2009
11-5 UPDATE!
Hi folks,
Things are progressing well. This Fri. & Sat. it looks like we'll be working on final finish trim work, painting touch-up, kitchen flooring & cabinets, and if the weather holds some additional lawn work.
Hope to see you there.
Regards,Bruce
PS. The dedication for this house has been set for Sunday, November 22nd at 2 PM!
Things are progressing well. This Fri. & Sat. it looks like we'll be working on final finish trim work, painting touch-up, kitchen flooring & cabinets, and if the weather holds some additional lawn work.
Hope to see you there.
Regards,Bruce
PS. The dedication for this house has been set for Sunday, November 22nd at 2 PM!