Hi folks,
We're underway! The foundation is going in. The new site address is 266 Bridge St. in Corning. That's right at the very end of Bridge St. before the railroad tracks.
This week the first tasks will be installing plastic and radon venting in the crawl space along with completing the floor joists and decking.
Next week there are several special work days:
Wed., 5/5 - Elmira college students will be coming to work finishing the floor decking and/or building the storage shed
Fri. 5/7 - Women's Build (sponsored by Lowes) - framing exterior walls
Sat., 5/8 - carpenter's union erecting roof trusses, installing decking and shingles (no regular volunteers this day)
The week of May 10 we'll be starting our regular work schedule of Wed. and Sat., 8:30-3:00.
Regards,
Bruce
Sunday, April 25, 2010
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment