Thursday, April 29, 2010

4-29 UPDATE!

Hi folks,

The foundation is poured. We're ready to go! For anyone who is available, we'll be working both Fri., 4/30 and Sat., 5/1, from 8:00-3:30. We'll be installing the floor joists and support system, and laying the subfloor plywood. There will be lots of hammering to do. Hope to see you there.

Regards,
Bruce

Sunday, April 25, 2010

4-25 CONSTRUCTION UPDATE!

Hi folks,

We're underway! The foundation is going in. The new site address is 266 Bridge St. in Corning. That's right at the very end of Bridge St. before the railroad tracks.

This week the first tasks will be installing plastic and radon venting in the crawl space along with completing the floor joists and decking.

Next week there are several special work days:

Wed., 5/5 - Elmira college students will be coming to work finishing the floor decking and/or building the storage shed

Fri. 5/7 - Women's Build (sponsored by Lowes) - framing exterior walls

Sat., 5/8 - carpenter's union erecting roof trusses, installing decking and shingles (no regular volunteers this day)

The week of May 10 we'll be starting our regular work schedule of Wed. and Sat., 8:30-3:00.

Regards,
Bruce

Friday, April 9, 2010

CONSTRUCTION IS STARTING!

Planning has been underway for the build projects for this year. We are going to busy!

First, we will be building a construction storage shed at the ReStore site on Route 414 in Corning. The main building there will be done by a combination of the students from the Ithaca College Campus Chapter and local State Farm agents to celebrate the successful completion of the requirements for Ithaca College HFH to receive a $5,000 grant from State Farm. Combined with the $5,000 raised by the students, SESC Habitat will be receiving $10,000 for our building fund! This group day is scheduled for Satuday, April 24th.

Then work will start on the first house we will be building this year at 266 Bridge St. in Corning. Keep checking bac for updates on the progress there.

Here's the first posting from Bruce Peffley, our construction team leader:

Hi folks,
Here's the current plan for the several weeks.

Set forms and pour concrete pad for a new construction shop area at the Restore. (W, 4/14, 8:00 AM ; rain date F, 4/16 or Sat, 4/17)

Assuming the foundation (at 266 Bridge St.) gets completed, we'll start working regularly on Wednesdays beginning 4/21- our initial tasks are to complete the center support beam; floor joists and decking; foundation drainage, radon piping, plastic film & gravel in crawl space. The goal is to be ready for framing the exterior walls during the Women's Build on F, 5/7.

If you're available to help supervise, a group of Ithaca College students and State Farm employees are going to be working on building the construction shop on Sat., 4/24. (The IC student chapter was awarded a grant from State Farm to aid our projects.)

Regards,
Bruce